BetaSuspendedBatteryPSELBNL
100 MW storage in Pierce, WA · In queue since April 2020 · Proposed COD April 2023
100 MW
Capacity
1
Components
Battery
5y 11m
In Queue
Suspended
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3 years
Suspended38%
Queue EntryApr 27, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-04-01
Project Details
State
WA
County
Pierce
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Fredrickson Plant 115kV Substation
Data Source
LBNL
No news available for this project.