— Project Summary

Queue ID
PSE-81
Capacity
100 MW
Technology
Battery
Status
suspended
Location
Pierce, WA
Region
West
Developer
IA Status
Suspended

BetaSuspendedBatteryPSELBNL

100 MW storage in Pierce, WA · In queue since April 2020 · Proposed COD April 2023

100 MW

Capacity

1

Components

Battery

5y 11m

In Queue

Suspended

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3 years

Suspended38%
Queue EntryApr 27, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-04-01

Project Details

State

WA

County

Pierce

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Fredrickson Plant 115kV Substation

Data Source

LBNL

No news available for this project.