BetaSuspendedSolarPSELBNL
100.6 MW generation in Douglas, WA · In queue since January 2018 · Proposed COD December 2023
100.6 MW
Capacity
1
Components
Solar
8y 2m
In Queue
Suspended
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
5y 11m
Suspended38%
Queue EntryJan 8, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
WA
County
Douglas
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Cascade - Rocky Reach 230kV Line
Data Source
LBNL
No news available for this project.