— Project Summary

Queue ID
PSE-52
Capacity
20 MW
Technology
Wind
Status
suspended
Location
Kittitas, WA
Region
West
Developer
IA Status
Suspended

BetaSuspendedWindPSELBNL

20 MW generation in Kittitas, WA · In queue since October 2017 · Proposed COD December 2025

20 MW

Capacity

1

Components

Wind

8y 5m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

8y 2m

Suspended38%
Queue EntryOct 16, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

WA

County

Kittitas

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Cascade-Rocky Reach 230 kV Line

Data Source

LBNL

No news available for this project.