BetaSuspendedWindPSELBNL
20 MW generation in Kittitas, WA · In queue since October 2017 · Proposed COD December 2025
20 MW
Capacity
1
Components
Wind
8y 5m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
8y 2m
Suspended38%
Queue EntryOct 16, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
WA
County
Kittitas
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Cascade-Rocky Reach 230 kV Line
Data Source
LBNL