— Project Summary

Queue ID
PSE-51
Capacity
79.2 MW
Technology
Solar
Status
suspended
Location
Kittitas, WA
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarPSELBNL

79.2 MW generation in Kittitas, WA · In queue since September 2017 · Proposed COD December 2024

79.2 MW

Capacity

1

Components

Solar

8y 6m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

7y 3m

Suspended38%
Queue EntrySep 13, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

WA

County

Kittitas

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Cascade-Rocky Reach 230 kV Line

Data Source

LBNL

No news available for this project.