BetaActiveSolarPSELBNL
100 MW generation in Kittitas, WA · In queue since April 2017 · Proposed COD December 2023
100 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
6y 8m
Schedule
27 months past proposed COD
Construction75%
Queue EntryApr 25, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
WA
County
Kittitas
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Wind Ridge 230kV Substation
Data Source
LBNL
No news available for this project.