— Project Summary

Queue ID
PSE-49
Capacity
100 MW
Technology
Solar
Status
active
Location
Kittitas, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarPSELBNL

100 MW generation in Kittitas, WA · In queue since April 2017 · Proposed COD December 2023

100 MW

Capacity

1

Components

Solar

8y 11m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

6y 8m

Schedule

27 months past proposed COD

Construction75%
Queue EntryApr 25, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

WA

County

Kittitas

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Wind Ridge 230kV Substation

Data Source

LBNL

No news available for this project.