— Project Summary

Queue ID
PSE-46
Capacity
136.8 MW
Technology
Wind
Status
active
Location
Lewis, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveWindPSELBNL

136.8 MW generation in Lewis, WA · In queue since January 2016 · Proposed COD December 2019

136.8 MW

Capacity

1

Components

Wind

10y 2m

In Queue

IA Executed

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

3y 11m

Schedule

76 months past proposed COD

Construction75%
Queue EntryJan 19, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2019-12-27

Project Details

State

WA

County

Lewis

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Tono Substation

Data Source

LBNL

No news available for this project.