— Project Summary

Queue ID
PSE-152
Capacity
188 MW
Technology
Gas
Status
active
Location
Whatcom, WA
Region
West
Developer
IA Status
Cluster Study

BetaActiveGasPSELBNL

188 MW generation in Whatcom, WA · In queue since April 2024 · Proposed COD December 2028

188 MW

Capacity

1

Components

Gas

1y 11m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 8m

Impact Study25%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

WA

County

Whatcom

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Arco Central 115kV Substation

Data Source

LBNL