BetaActiveGasPSELBNL
188 MW generation in Whatcom, WA · In queue since April 2024 · Proposed COD December 2028
188 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 8m
Impact Study25%
Queue EntryApr 17, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
WA
County
Whatcom
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Arco Central 115kV Substation
Data Source
LBNL