BetaActiveBatteryPSELBNL
100 MW storage in King, WA · In queue since April 2024 · Proposed COD October 2028
100 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 6m
Impact Study25%
Queue EntryApr 17, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-31
Project Details
State
WA
County
King
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Sedro-Woolley 230 kV Substation
Data Source
LBNL
No news available for this project.