— Project Summary

Queue ID
PSE-145
Capacity
100 MW
Technology
Battery
Status
active
Location
Whatcom, WA
Region
West
Developer
IA Status
Cluster Study

BetaActiveBatteryPSELBNL

100 MW storage in Whatcom, WA · In queue since April 2024 · Proposed COD May 2027

100 MW

Capacity

1

Components

Battery

1y 11m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 1m

Impact Study25%
Queue EntryApr 12, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-31

Project Details

State

WA

County

Whatcom

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Custer Substation (48.90451433, -122.6251608)

Data Source

LBNL

No news available for this project.