300 MW hybrid in Thurston, WA · In queue since February 2024 · Proposed COD November 2030
300 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Cluster Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 9m
Impact Study25%
Queue EntryFeb 16, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-11-30
Project Details
State
WA
County
Thurston
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Tono 115kV Substation
Data Source
LBNL
No news available for this project.