— Project Summary

Queue ID
PSE-141
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Thurston, WA
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarWindBatteryPSELBNL

300 MW hybrid in Thurston, WA · In queue since February 2024 · Proposed COD November 2030

300 MW

Capacity

1

Components

Solar

2y 1m

In Queue

Cluster Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 9m

Impact Study25%
Queue EntryFeb 16, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-11-30

Project Details

State

WA

County

Thurston

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Tono 115kV Substation

Data Source

LBNL

No news available for this project.