— Project Summary

Queue ID
PSE-139
Capacity
130 MW
Technology
Battery
Status
active
Location
King, WA
Region
West
Developer
IA Status
Cluster Study

BetaActiveBatteryPSELBNL

130 MW storage in King, WA · In queue since December 2023 · Proposed COD December 2028

130 MW

Capacity

1

Components

Battery

2y 3m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5 years

Impact Study25%
Queue EntryDec 15, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-30

Project Details

State

WA

County

King

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Mount Si 115 kV Substation

Data Source

LBNL