BetaActiveBatteryPSELBNL
130 MW storage in King, WA · In queue since December 2023 · Proposed COD December 2028
130 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5 years
Impact Study25%
Queue EntryDec 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-30
Project Details
State
WA
County
King
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Mount Si 115 kV Substation
Data Source
LBNL
No news available for this project.