— Project Summary

Queue ID
PSE-133
Capacity
300 MW
Technology
Solar
Status
active
Location
Garfield, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarPSELBNL

300 MW generation in Garfield, WA · In queue since May 2022 · Proposed COD December 2025

300 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 7m

Schedule

3 months past proposed COD

Facilities Study50%
Queue EntryMay 19, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-15

Project Details

State

WA

County

Garfield

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Dodge Junction 230 kV Substation

Data Source

LBNL

No news available for this project.