150 MW hybrid in Garfield, WA · In queue since August 2021 · Proposed COD December 2024
150 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 4m
Schedule
15 months past proposed COD
In Study38%
Queue EntryAug 27, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
WA
County
Garfield
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Phalen Gulch 230 kV Substation
Data Source
LBNL