— Project Summary

Queue ID
PSE-121
Capacity
125 MW
Technology
Battery
Status
suspended
Location
King, WA
Region
West
Developer
IA Status
Suspended

BetaSuspendedBatteryPSELBNL

125 MW storage in King, WA · In queue since August 2021 · Proposed COD July 2024

125 MW

Capacity

1

Components

Battery

4y 7m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 11m

Suspended38%
Queue EntryAug 25, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-07-01

Project Details

State

WA

County

King

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Starwood 115 kV

Data Source

LBNL

No news available for this project.