218.78 MW generation in Lewis, WA · In queue since July 2021 · Proposed COD October 2025
218.78 MW
Capacity
1
Components
Gas
4y 8m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 3m
Suspended38%
Queue EntryJul 27, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-15
Project Details
State
WA
County
Lewis
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Primary: Proposed new 115 kV substation between Tono, Blumaer, and Rochester substations
Data Source
LBNL