— Project Summary

Queue ID
PSE-112
Capacity
127 MW
Technology
Battery
Status
active
Location
Thurston, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveBatteryPSELBNL

127 MW storage in Thurston, WA · In queue since June 2021 · Proposed COD June 2025

127 MW

Capacity

1

Components

Battery

4y 9m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4 years

Schedule

9 months past proposed COD

Construction75%
Queue EntryJun 23, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-06-15

Project Details

State

WA

County

Thurston

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Proposed new 115 kV substation between Tono, Blumaer, and Rochester substations

Data Source

LBNL

No news available for this project.