— Project Summary

Queue ID
PSE-110
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Garfield, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryPSELBNL

150 MW hybrid in Garfield, WA · In queue since June 2021 · Proposed COD December 2024

150 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 6m

Schedule

15 months past proposed COD

Construction75%
Queue EntryJun 18, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

WA

County

Garfield

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Phalen Gulch 230 kV Substation

Data Source

LBNL

No news available for this project.