— Project Summary

Queue ID
PSE-109
Capacity
200 MW
Technology
Battery
Status
active
Location
Kitsap, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveBatteryPSELBNL

200 MW storage in Kitsap, WA · In queue since May 2021 · Proposed COD December 2023

200 MW

Capacity

1

Components

Battery

4y 10m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 7m

Schedule

28 months past proposed COD

Construction75%
Queue EntryMay 27, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2023-12-15

Project Details

State

WA

County

Kitsap

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

South Bremerton 115kV Substation

Data Source

LBNL

No news available for this project.