BetaActiveBatteryPSELBNL
200 MW storage in King, WA · In queue since April 2021 · Proposed COD January 2024
200 MW
Capacity
1
Components
Battery
4y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 9m
Schedule
27 months past proposed COD
Construction75%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2024-01-06
Project Details
State
WA
County
King
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Sedro Wooley 230 kV Substation
Data Source
LBNL