150 MW storage in Skagit, WA · In queue since April 2021 · Proposed COD January 2024
150 MW
Capacity
1
Components
Battery
4y 11m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 9m
Suspended38%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-01-06
Project Details
State
WA
County
Skagit
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
St. Clair 230 kV Substation Tono 115 kV
Data Source
LBNL
No news available for this project.