— Project Summary

Queue ID
PSCo-GI-2024-19
Capacity
199 MW
Technology
Solar+Battery
Status
active
Location
Lincoln, CO
Region
West
Developer
IA Status

BetaActiveSolarBatteryPSCoLBNL

199 MW hybrid in Lincoln, CO · In queue since May 2024 · Proposed COD May 2028

199 MW

Capacity

1

Components

Solar

1y 10m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

Pre-Study0%
Queue EntryMay 17, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-05

Project Details

State

CO

County

Lincoln

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Pronghorn-Missile Site 345 kV line

Data Source

LBNL