100 MW generation in Alamosa, CO · In queue since May 2024 · Proposed COD January 2030
100 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 8m
Pre-Study0%
Queue EntryMay 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-01-01
Project Details
State
CO
County
Alamosa
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
San Luis Valley 230 kV Substation
Data Source
LBNL