— Project Summary

Queue ID
PSCo-GI-2024-16
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Kiowa, CO
Region
West
Developer
IA Status

BetaActiveSolarBatteryPSCoLBNL

250 MW hybrid in Kiowa, CO · In queue since May 2024 · Proposed COD December 2027

250 MW

Capacity

1

Components

Solar

1y 10m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 7m

Pre-Study0%
Queue EntryMay 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

CO

County

Kiowa

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Boone-Lamar 230 kV line

Data Source

LBNL

No news available for this project.