— Project Summary

Queue ID
PSCo-GI-2024-15
Capacity
110 MW
Technology
Solar+Battery
Status
active
Location
Alamosa, CO
Region
West
Developer
IA Status

BetaActiveSolarBatteryPSCoLBNL

110 MW hybrid in Alamosa, CO · In queue since May 2024 · Proposed COD May 2028

110 MW

Capacity

1

Components

Solar

1y 10m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-30

Project Details

State

CO

County

Alamosa

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

San Luis Valley 230 kV Substation

Data Source

LBNL

No news available for this project.