— Project Summary

Queue ID
PSCo-GI-2024-09
Capacity
199 MW
Technology
Battery
Status
active
Location
Adams, CO
Region
West
Developer
IA Status

BetaActiveBatteryPSCoLBNL

199 MW storage in Adams, CO · In queue since May 2024 · Proposed COD December 2027

199 MW

Capacity

1

Components

Battery

1y 10m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 7m

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-15

Project Details

State

CO

County

Adams

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Riverdale 230 kV Substation

Data Source

LBNL

No news available for this project.