BetaActiveBatteryPSCoLBNL
10 MW storage in Pueblo, CO · In queue since May 2024 · Proposed COD March 2026
10 MW
Capacity
1
Components
Battery
1y 10m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
1y 10m
Pre-Study0%
Queue EntryMay 14, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Comanche 345 kV Substation
Data Source
LBNL