BetaActiveSolarBatteryPSCoLBNL
100 MW hybrid in Pueblo, CO · In queue since May 2024 · Proposed COD May 2028
100 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
Pre-Study0%
Queue EntryMay 10, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-15
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Comanche 115 kV Substation
Data Source
LBNL
No news available for this project.