BetaActiveSolarBatteryPSCoLBNL
400 MW hybrid in Pueblo, CO · In queue since April 2024 · Proposed COD March 2028
400 MW
Capacity
1
Components
Solar
1y 11m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Pre-Study0%
Queue EntryApr 29, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Daniels Park-Tundra 345 kV line
Data Source
LBNL
No news available for this project.