— Project Summary

Queue ID
PSCo-GI-2024-04
Capacity
100 MW
Technology
Solar
Status
active
Location
Pueblo, CO
Region
West
Developer
IA Status

BetaActiveSolarPSCoLBNL

100 MW generation in Pueblo, CO · In queue since April 2024 · Proposed COD June 2028

100 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 2m

Pre-Study0%
Queue EntryApr 26, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

CO

County

Pueblo

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Mirasol 230 kV Substation

Data Source

LBNL

No news available for this project.