— Project Summary

Queue ID
PSCo-GI-2024-03
Capacity
150 MW
Technology
Solar
Status
active
Location
Adams, CO
Region
West
Developer
IA Status

BetaActiveSolarPSCoLBNL

150 MW generation in Adams, CO · In queue since April 2024 · Proposed COD March 2029

150 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 11m

Pre-Study0%
Queue EntryApr 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-25

Project Details

State

CO

County

Adams

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Pawnee-Missile Site 230 kV line

Data Source

LBNL

No news available for this project.