BetaActiveSolarBatteryPSCoLBNL
199 MW hybrid in Weld, CO · In queue since April 2024 · Proposed COD May 2027
199 MW
Capacity
1
Components
Solar
1y 11m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
Pre-Study0%
Queue EntryApr 5, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-30
Project Details
State
CO
County
Weld
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Canal Crossing - Ft St Vrain 345 kV line
Data Source
LBNL
No news available for this project.