BetaActiveWindPSCoLBNL
400 MW generation in Morgan, CO · In queue since May 2023 · Proposed COD October 2026
400 MW
Capacity
1
Components
Wind
2y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 5m
In Study38%
Queue EntryMay 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-01
Project Details
State
CO
County
Morgan
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Pawnee Substation 345 kV
Data Source
LBNL
No news available for this project.