— Project Summary

Queue ID
PSCo-GI-2022-1
Capacity
52 MW
Technology
Gas
Status
active
Location
Weld, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveGasPSCoLBNL

52 MW generation in Weld, CO · In queue since March 2022 · Proposed COD April 2023

52 MW

Capacity

1

Components

Gas

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

1y 1m

Schedule

36 months past proposed COD

In Study38%
Queue EntryMar 22, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-04-01

Project Details

State

CO

County

Weld

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Rocky Mountain Energy Center Unit 1 and Unit 2

Data Source

LBNL

No news available for this project.