52 MW generation in Weld, CO · In queue since March 2022 · Proposed COD April 2023
52 MW
Capacity
1
Components
Gas
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 1m
Schedule
36 months past proposed COD
In Study38%
Queue EntryMar 22, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-04-01
Project Details
State
CO
County
Weld
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Rocky Mountain Energy Center Unit 1 and Unit 2
Data Source
LBNL