199 MW hybrid in Adams, CO · In queue since April 2021 · Proposed COD December 2024
199 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 8m
Schedule
15 months past proposed COD
Construction75%
Queue EntryApr 2, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
CO
County
Adams
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Green Valley - Sky Ranch 230 kV
Data Source
LBNL