BetaActiveGasPSCoLBNL
35 MW generation in Weld, CO · In queue since March 2021 · Proposed COD November 2021
35 MW
Capacity
1
Components
Gas
5 years
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
8 months
Schedule
54 months past proposed COD
Construction75%
Queue EntryMar 22, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2021-11-01
Project Details
State
CO
County
Weld
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Fort St Vrain Unit #3
Data Source
LBNL