— Project Summary

Queue ID
PSCo-GI-2021-3
Capacity
35 MW
Technology
Gas
Status
active
Location
Weld, CO
Region
West
Developer
IA Status
IA Executed

BetaActiveGasPSCoLBNL

35 MW generation in Weld, CO · In queue since March 2021 · Proposed COD November 2021

35 MW

Capacity

1

Components

Gas

5 years

In Queue

IA Executed

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

8 months

Schedule

54 months past proposed COD

Construction75%
Queue EntryMar 22, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2021-11-01

Project Details

State

CO

County

Weld

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Fort St Vrain Unit #3

Data Source

LBNL

No news available for this project.