BetaSuspendedSolarBatteryPSCoLBNL
374 MW hybrid in Pueblo, CO · In queue since September 2020 · Proposed COD December 2024
374 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 3m
Suspended38%
Queue EntrySep 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Boone-Midway 230 kV line
Data Source
LBNL
No news available for this project.