— Project Summary

Queue ID
PSCo-GI-2020-13
Capacity
374 MW
Technology
Solar+Battery
Status
suspended
Location
Pueblo, CO
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryPSCoLBNL

374 MW hybrid in Pueblo, CO · In queue since September 2020 · Proposed COD December 2024

374 MW

Capacity

1

Components

Solar

5y 6m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

4y 3m

Suspended38%
Queue EntrySep 22, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-01

Project Details

State

CO

County

Pueblo

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Boone-Midway 230 kV line

Data Source

LBNL

No news available for this project.