— Project Summary

Queue ID
PSCo-GI-2020-05
Capacity
24 MW
Technology
Gas
Status
active
Location
Weld, CO
Region
West
Developer
IA Status
IA Executed

BetaActiveGasPSCoLBNL

24 MW generation in Weld, CO · In queue since March 2020 · Proposed COD November 2020

24 MW

Capacity

1

Components

Gas

6 years

In Queue

IA Executed

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

8 months

Schedule

66 months past proposed COD

Construction75%
Queue EntryMar 9, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2020-11-01

Project Details

State

CO

County

Weld

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Ft. St. Vrain

Data Source

LBNL

No news available for this project.