— Project Summary

Queue ID
PSCo-GI-2020-03
Capacity
199 MW
Technology
Solar
Status
suspended
Location
Pueblo, CO
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarPSCoLBNL

199 MW generation in Pueblo, CO · In queue since March 2020 · Proposed COD December 2023

199 MW

Capacity

1

Components

Solar

6 years

In Queue

Suspended

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 9m

Suspended38%
Queue EntryMar 9, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-01

Project Details

State

CO

County

Pueblo

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Boone-Comanche 230 kV line

Data Source

LBNL