BetaActiveWindPSCoLBNL
300 MW generation in Lincoln, CO · In queue since February 2016
300 MW
Capacity
1
Components
Wind
10y 1m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
10y 1m
Construction75%
Queue EntryFeb 24, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
CO
County
Lincoln
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Missile Site Substation
Data Source
LBNL