BetaSuspendedWindPSCoLBNL
200 MW generation in Lincoln, CO · In queue since July 2016
200 MW
Capacity
1
Components
Wind
9y 8m
In Queue
Suspended
IA Status
Interconnection Timeline
Total Duration
9y 8m
Suspended38%
Queue EntryJul 28, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
CO
County
Lincoln
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Missile Site 345kV
Data Source
LBNL