BetaActiveBatteryPSCoLBNL
200 MW storage in Arapahoe, CO · In queue since September 2022 · Proposed COD December 2025
200 MW
Capacity
1
Components
Battery
3y 6m
In Queue
IA Pending
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 3m
Schedule
4 months past proposed COD
In Study38%
Queue EntrySep 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
CO
County
Arapahoe
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Missile Site 345 kV Substation
Data Source
LBNL