— Project Summary

Queue ID
PSCo-GI-2011-2 & 7
Capacity
200 MW
Technology
Battery
Status
active
Location
Arapahoe, CO
Region
West
Developer
IA Status
IA Pending

BetaActiveBatteryPSCoLBNL

200 MW storage in Arapahoe, CO · In queue since September 2022 · Proposed COD December 2025

200 MW

Capacity

1

Components

Battery

3y 6m

In Queue

IA Pending

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 3m

Schedule

4 months past proposed COD

In Study38%
Queue EntrySep 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

CO

County

Arapahoe

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Missile Site 345 kV Substation

Data Source

LBNL

No news available for this project.