— Project Summary

Queue ID
PSCo-3RSC-2023-03
Capacity
200 MW
Technology
Wind
Status
active
Location
Kiowa, CO
Region
West
Developer
IA Status

BetaActiveWindPSCoLBNL

200 MW generation in Kiowa, CO · In queue since May 2023 · Proposed COD December 2025

200 MW

Capacity

1

Components

Wind

2y 10m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 7m

Schedule

3 months past proposed COD

Pre-Study0%
Queue EntryMay 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

CO

County

Kiowa

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

May Valley 345 kV

Data Source

LBNL

No news available for this project.