— Project Summary

Queue ID
PSCo-2RSC-2020-05
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Pueblo, CO
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryPSCoLBNL

250 MW hybrid in Pueblo, CO · In queue since September 2020 · Proposed COD September 2022

250 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2 years

Schedule

42 months past proposed COD

Construction75%
Queue EntrySep 10, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2022-09-30

Project Details

State

CO

County

Pueblo

Region

West

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Point of Interconnection

Mirasol Switchyard on the Comanche- Midway 230 kV Transmission Line

Data Source

LBNL

No news available for this project.