250 MW hybrid in Pueblo, CO · In queue since September 2020 · Proposed COD September 2022
250 MW
Capacity
1
Components
Solar
5y 6m
In Queue
IA Executed
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2 years
Schedule
42 months past proposed COD
Construction75%
Queue EntrySep 10, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2022-09-30
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Mirasol Switchyard on the Comanche- Midway 230 kV Transmission Line
Data Source
LBNL