75 MW storage in Pueblo, CO · In queue since January 2020 · Proposed COD December 2022
75 MW
Capacity
1
Components
Battery
6y 2m
In Queue
IA Executed
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 11m
Schedule
40 months past proposed COD
Construction75%
Queue EntryJan 24, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2022-12-01
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Point of Interconnection
Comanche-Daniels Park 345 kV
Data Source
LBNL