— Project Summary

Queue ID
PRPA-24-10021
Capacity
10 MW
Technology
Solar
Status
active
Location
Larimer, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPRPALBNL

10 MW generation in Larimer, CO · In queue since October 2024 · Proposed COD June 2026

10 MW

Capacity

1

Components

Solar

1y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

1y 8m

In Study38%
Queue EntryOct 2, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

Project Details

State

CO

County

Larimer

Region

West

Developer

Utility

Platte River Power Authority

Entity

PRPA

Point of Interconnection

Ault-Carey 230kV

Data Source

LBNL

No news available for this project.