BetaActiveBatteryPRPALBNL
50 MW storage in Larimer, CO · In queue since May 2023 · Proposed COD January 2026
50 MW
Capacity
1
Components
Battery
2y 10m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 8m
Schedule
3 months past proposed COD
Impact Study25%
Queue EntryMay 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-01
Project Details
State
CO
County
Larimer
Region
West
Developer
—
Utility
Platte River Power Authority
Entity
PRPA
Point of Interconnection
Ault-Carey 230kV
Data Source
LBNL