— Project Summary

Queue ID
PRPA-22-07254
Capacity
10 MW
Technology
Battery
Status
active
Location
Weld, CO
Region
West
Developer
IA Status
System Impact Study

BetaActiveBatteryPRPALBNL

10 MW storage in Weld, CO · In queue since July 2022 · Proposed COD March 2026

10 MW

Capacity

1

Components

Battery

3y 8m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

Schedule

1 months past proposed COD

Impact Study25%
Queue EntryJul 25, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-01

Project Details

State

CO

County

Weld

Region

West

Developer

Utility

Platte River Power Authority

Entity

PRPA

Point of Interconnection

Longs Peak 230kV

Data Source

LBNL

No news available for this project.