— Project Summary

Queue ID
PRPA-22-07252
Capacity
200 MW
Technology
Wind+Battery
Status
active
Location
Larimer, CO
Region
West
Developer
IA Status
System Impact Study

BetaActiveWindBatteryPRPALBNL

200 MW hybrid in Larimer, CO · In queue since July 2022 · Proposed COD March 2026

200 MW

Capacity

1

Components

Wind

3y 8m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

Schedule

1 months past proposed COD

Impact Study25%
Queue EntryJul 25, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-01

Project Details

State

CO

County

Larimer

Region

West

Developer

Utility

Platte River Power Authority

Entity

PRPA

Point of Interconnection

Rawhide-Roundhouse 230kV

Data Source

LBNL

No news available for this project.