250 MW hybrid in Larimer, CO · In queue since July 2022 · Proposed COD March 2028
250 MW
Capacity
1
Components
Gas
3y 8m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 8m
Impact Study25%
Queue EntryJul 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
CO
County
Larimer
Region
West
Developer
—
Utility
Platte River Power Authority
Entity
PRPA
Point of Interconnection
Rawhide 230kV
Data Source
LBNL
No news available for this project.