BetaActiveSolarBatteryPRPALBNL
125 MW hybrid in Larimer, CO · In queue since November 2021 · Proposed COD December 2026
125 MW
Capacity
1
Components
Solar
4y 4m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 1m
Impact Study25%
Queue EntryNov 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
CO
County
Larimer
Region
West
Developer
—
Utility
Platte River Power Authority
Entity
PRPA
Point of Interconnection
Ault-Carey 230kV
Data Source
LBNL
No news available for this project.